Report #21-E-0033, December 7, 2020
Without improved management controls, the EPA risks continued cost overruns and delays in its laboratory consolidation efforts. Overruns and delays will reduce the Agency’s potential avoided costs and savings of approximately $409 million over 30 years.
Report Materials
Without improved management controls, the EPA risks continued cost overruns and delays in its laboratory consolidation efforts. Overruns and delays will reduce the Agency’s potential avoided costs and savings of approximately $409 million over 30 years.
Report Materials
This report relates to: Project #OA&E-FY20-0353